Project Management in the Chemical Industry.


Temporary Sheds

- Before erecting temporary shelters like sheds or tents anywhere at site, written permission of the concerned Engineer In-charge must be obtained.

- It is advisable that temporary sheds should be avoided for site offices. It is better to use porta cabins for site office and stores.

- Temporary shed should not be erected using scaffolding pipes. The shed should be made of safe construction material.

- The temporary shed should be erected after proper designing following engineering design practices in conformance with normal safety standards to ensure the stability and safety.

- Temporary piping, hose connections and electrical wiring to these temporary sheds must be laid in such manner that they do not cause tripping, hitting or electrocution hazards.